Anthropic buys $3.4 billion of gas generators for its data centers, FT reports
Redacción IvokaNov 10, 10:30 AM 3 min
According to the Financial Times, Anthropic took over orders for 1.7 gigawatts of generators from OnePWR. The Next Web could not independently confirm the deal.
The Financial Times reported that Anthropic agreed to pay $3.4 billion for gas-fired generators to power its data centers, according to Tom's Hardware.
Key facts:
- The deal covers 1.7 gigawatts of large generators, taking over Caterpillar orders previously placed by OnePWR Solutions, a San Antonio, Texas company. It also covers the work needed to install the equipment.
- It was signed in late September.
- OnePWR ordered the generators from Caterpillar about two years ago but needed money to complete the purchase. Anthropic had first planned to buy power from OnePWR and instead took over the orders.
- Anthropic did not buy OnePWR as a company and none of its staff moved to Anthropic, according to the FT.
- It is not known where the generators will be used.
- According to Tom's Hardware, orders for large gas turbines and generators are piling up and manufacturers are struggling to keep pace, especially with demand from AI companies. It reports average delivery times in the U.S. have reached six years.
- The Next Web notes that it could not independently confirm the deal. Both companies declined to comment to the FT.
Context: the deal comes as Anthropic prepares for its stock market listing. Its amended filing shows $895 billion in commitments, almost all for computing power and infrastructure. Other AI firms have also turned to gas to get data centers running quickly; Elon Musk's xAI faces a lawsuit over gas turbines at its Memphis site.
Why it matters to Ivoka's community: because it shows AI companies are locking up large amounts of power equipment to run their data centers, an issue that goes beyond software.
Sources
- The Next Web: https://thenextweb.com/news/anthropic-3-4bn-gas-generators-onepwr-ft
- Channel Insider: https://www.channelinsider.com/infrastructure/news-anthropic-3-4b-ai-data-center-generators/
- Tom's Hardware: https://www.tomshardware.com/tech-industry/data-centers/anthropic-skips-six-year-waitlist-with-massive-usd3-4-billion-gas-turbine-generator-deal-firm-takes-over-onepwrs-orders-secures-1-7gw-of-capacity-to-power-ai-data-centers